I'm discussing from a builders' POV.I'm relaying what the technical team at Celotex told me.
None of the full fill rebated PIR systems we have used have required fasteners. They are designed so that the inner or outer leaf can be built first.
All cavities need to be at least 10mm bigger than the product simply to make them fit.
There isn't a builder or robot on the planet that can build two leaves of masonry walls and maintain a constant 10mm gap.