    RSJ fitting not flush

    Hi Guys thank you all so much for the comments, the builder as told me he didn't push it back because there was a concrete lintel in the way on the inner leaf he said when he gets the second steel in place he will push the outer leaf steel back to meet it, I doubt this was his intention from the...
  2. C

    RSJ fitting not flush

    I think this needs to be redone, the inner and outer leaf plus the cavity = 270mm the 2 RSJ,s when bolted tight together = 266mm One of the RSJ,s has spacers, so padstone to cross the cavity at same width of the 2 RSJ,s..but I will need to find a padstone to fit, the SE asks for 400mm x 100 x...
  3. C

    RSJ fitting not flush

    Sorry Tony about 15mm off center.
  4. C

    RSJ fitting not flush

    Hi Tony Yes they are solid engineering bricks, I was thinking that the width of the steel wouldn't of been such a problem if the builder had kept the web central to the brick and slightly overhang the cavity, yes I agree the specs on the plan says 133 the builder may of put it central if it were...
  5. C

    RSJ fitting not flush

    Or both!! I have read that the web of the rsj should be central to the brick and this is not central. Thanks Woody
  6. C

    RSJ fitting not flush

    Thanks Woody, The plasterboard on the extention side will be dot and dab so should hide the overhang, but I was abit dubious about the amount of overhang! Would this pass a building inspection?
  7. C

    RSJ fitting not flush

    Hi I am having a rsj fitted thats 203 x 133 x 25 There are 2 of them one for inner and one for outer leaf they are 3.6m long. The outer leaf rsj as been fitted but I'm unsure if it's correct I was expecting it to sit flush to the outer brick work but it sits proud about 25mm to 30mm see pic, am...
  8. C

    Bi folds Gap

    Thank you everyone for the replies, Yes it's really bugging me and I doubt I could unsee it, I was thinking of adding a angle trim that sits on the bricks just above the front edge of the rsj but lower down on the larger gap side, I just want to try and minimise how noticible it would be.
  9. C

    Bi folds Gap

    Hi Could someone advise me on the best way to trim this sloping gap. I have just put the bifold in place and realised that the steel is not level! Over the 3m length it's probably around 20mm out..but once fitted how do I trim so the slope is not noticeable. The builder as done a runner so no...
  10. C

    Concrete roof tiles

    Ah yes that makes perfect sense! Brilliant thanks so much.
  11. C

    Concrete roof tiles

    Can I just ask why the right? And is that my right stood facing the front.
  12. C

    Concrete roof tiles

    Ok thank you.
  13. C

    Concrete roof tiles

    Thank you and would it matter if that cut was on the raised part of the profile or the lower part.
  14. C

    Concrete roof tiles

    Hi I have Redland Regent size roof tiles my extension is 9m length the size is 418 x 332 mm and less interlock the size is 300mm wide. I can fit 30 tiles horizontally accounting for overhang I am still left with a gap at one side. Can I have cut tiles on just one side of the roof? And does it...
  15. C

    How long to tile a roof

    Ha ha...He's very temperamental, yes parts of the question were answered in another thread, thanks Woody.
  16. C

    How long to tile a roof

    Hi woody no just having a few disagreements with my builder/ roofer..I asked him to change the roof membrane has it as been uncovered for 6 months, so the job will be.. remove old membrane and remove battens first, then replace membrane refit battens then tile. I wanted a roofers opinion on how...
  17. C

    How long to tile a roof

    It a new build Blup.
  18. C

    How long to tile a roof

    Thank you for the reply.
  19. C

    How long to tile a roof

    Hi How long would it take to install a breather membrane, battens and redland regent roof tiles on a 36 Sqm roof? It as no awkward angles just a lean to extension.
  20. C

    Roof membrane

    Hi sorry for the late reply we have the redland regent tiles and yes there was a long delay waiting for them, but they have been on site now for over 2 months and still no roofer/builder.