Search results

  1. abuildingsite

    Difference in costs between neighbouring BC's

    AFAIK, since October 2010 local authority BC base their fees on an average hourly rate across the BCOs, with some nominal admin and management charges thrown in. Could be that Barnet just pay their BCOs more, or think inspecting windows take a lot more time than Brent do. 'Technically', BC...
  2. abuildingsite

    Difference in costs between neighbouring BC's

    Approved Inspectors cannot take on Regularisations, so you're stuck with the Barnet's charges. No way around it once the works are underway/complete.
  3. abuildingsite

    Building regs of putting a bedroom next to a kitchen

    No obvious issues with having a kitchen next to a bedroom in principle, but there are some things to consider. Access Escape in the event of a fire via a kitchen is insufficient, but this can be easily overcome through having a escape window to the bedroom. There are loads of other things to...
  4. abuildingsite

    £95 to Building Control for a replacement window? Really?

    FYI- 'installation of thermal insulation in a roof space or loft space where the work soley consists of that installation' does not require a Building Regs application under Schedule 4 of the Regs 2010- so you get that one for free :lol:
  5. abuildingsite

    Extension / Boundary issue

    I agree, their surveyor doesn't sound suitably qualified to understand the implications. re: your second point, it sounds like the retaining structure to these other houses is formed from sheet piles. Although the steel is relatively thin, the corrugated pattern (to allow interlocking and...
  6. abuildingsite

    New building regs

    Sounds like the BCO is asking for trouble (conflicts of interest etc) but £50 is a very good price for an accredited SAP report. Call me paranoid but I'd be suspicious of any BCO that recommended a 'mate' to do some work for you, which you'll just give back to him and he ticks off as ok.
  7. abuildingsite

    Toilet building regs

    Yes there is. AD G 2010: 4.15 and 4.17.
  8. abuildingsite

    Toilet building regs

    as long as there is a basin in the same room as the WC :)
  9. abuildingsite

    Conservatory - Mid ter House Advice needed Please Urgent

    Be careful in assuming this. Your foundation depth may not be deep but conversely it's not uncommon for houses to have extremely shallow foundations. You'll have a better idea if you excavate a trial hole to your foundation (along the line of your extension). If the conservatory is being...
  10. abuildingsite

    External insulation for a small out building

    There are plenty of products out there. The one I see most often is Sto render (although external insulation isn't common at all). However, I'm not sure how effective insulating one wall will be, presuming that your floor and roof are also uninsulated.
  11. abuildingsite

    Toilet requirements in shop development

    The answer will be in BS6465-1, but is based on the capacity of the shop, which you haven't mentioned. However, as it's just a renovation and not a change of use of new build, Building Inspector has no control over your sanitary provision (unless you're increasing capacity) which is probably...
  12. abuildingsite

    Terrace House Converted Into 2 Flats

    That wasn't just a list of Regs, that was a lists of Regs applicable to a material change of use. In my experience, less and less is left to discretion and a 'stab at it' doesn't do the job. Part E, for example, specifically necessitates that the building passes sound tests (with allowances...
  13. abuildingsite

    Terrace House Converted Into 2 Flats

    No it's not. As far as the Regs go, the applicable standards are exactly the same. See Regulation 5(g) quoted above, which would apply in both scenarios. As I said, most people aren't aware of this and the cost and work implications involved.
  14. abuildingsite

    4 year rule

    Agreed, but the inspector is still within his rights to serve a Contravention Notice on the works to highlight the illegal extension.
  15. abuildingsite

    Who gets the Completion Certificate

    It should be part of the form as Regulation 14 (5) states that a request for a Completion Certificate should be made at the time of application where an Full Plans Notice is submitted. Interestingly, this caveat is not included in the rules for Building Notices, allowing some unscrupulous BC...
  16. abuildingsite

    trees on clay

    It wouldn't surprise me on heavy clays with thirsty trees nearby. That being said, any BCO that asks for an engineer's justification beyond NHBC guidelines is more than likely just covering their back.
  17. abuildingsite

    4 year rule

    Private BC (Approved Inspectors) have no powers to accept applications for works which have already started. Any BC dept would reject any such attempt on sight (which they are entitled to do as even private inspectors have to notify the council of their intention to take on a job). You're...
  18. abuildingsite

    Who gets the Completion Certificate

    The original application form will have had two boxes for contacts- one for your agent and one for you, as the applicant. Most BC application forms will have a box on them which asks whether you want the Completion Certificate sent to the agent or application (owner). Whoever filled out the...
  19. abuildingsite

    trees on clay

    You do risk heave by ripping out trees and ignoring them completely. For me, it's not worth it for the sake of getting one over on the BCO, especially if it's your own house.
  20. abuildingsite

    Decking regulations...

    Experience and practical use of the guidance for level thresholds in AD C... Very very little are actual Regs, despite common misconceptions. Most of what people assume to be Regulations are only guidance and it's my job, as a professional, to interpret the guidance and apply it to the grey...