    Wet UFH recommendations

    Thanks for this @muggles. Am I right in thinking that with this system I'd have to have the UFH on at the same time as the house rads? My preference would be for a system which enables me to operate the UFH separately from the house heating. Would this simply be a 2-zone system?
  2. N

    Wet UFH recommendations

    Hi, I am planning to install a wet system in the next week or 2, prior to screed arrival for my new kitchen floor. Having done quite a bit of googling, I can't seem to find many impartial places of advice as to what's a half decent and not too pricey ufh system for approx 28m2 in a single...
  3. N

    110mm to sink waste

    That should do the trick nicely. I guess I could do that flush with the screed, then the 40mm pipes will continue to be accessible if there are any issues.
  4. N

    110mm to sink waste

    Hi all, I'm about to lay the 110mm soil pipe needed to route my kitchen sink, washing machine etc. to the main drain, before pouring the slab for the base of my new floor. I was planning on having bends vertically up through the slab in order to connect to 40mm waste pipe etc. Would welcome...
  5. N

    Temporary pier for RSJs - padstones required?

    The plan to take the 2 internal walls out first was so that I could progress the floor, including laying a soil pipe under the stairs which will need to run the length of the kitchen. The first third of the room (where the working kitchen is) is a floating floor on joists, with the last two...
  6. N

    Temporary pier for RSJs - padstones required?

    Hi all, I am building a side-return extension on my victorian terrace, removing 2 internal walls and 1 external wall. My plan is to remove the internal walls first, leaving small portions of the wall in place as temporary piers (the parts which join the external wall which will be removed when...
  7. N

    Pouring slabs at different times - connect with rebar/helibar?

    That's great, thanks. What length of steel do you think would be required to connect 2 x (3000mm x 2000mm) pads 100mm deep?
  8. N

    Pouring slabs at different times - connect with rebar/helibar?

    Hi, First time post - go easy on me. I'm building a side-return extension on my victorian terrace which also requires the removal of two internal walls which divide the kitchen into 3 rooms. To keep the house functional and to save money, my plan is to work my way back from the end of the...