Hey all
Been lurking for a while picking up some useful advice and just registered.
Bought a house which was in need of a fair bit of work but didn't have much money so have been slowly doing what I can myself (hence the username because I must be Barking Mad to have taken this on!). Before I bought the house the previous owner had a chemical DPC installed along one wall of the house which had been suffering from rising damp. This was injected from the outside only as it's a solid wall but the plaster on the inside remains and will need to be removed and replastered.
I contacted the company who did the DPC and they advise that the bottom metre of plaster needs to come off and be replastered with a 3:1 sand/cement mix with a salt retardand additive. Now my understanding is that where plaster has suffered from damp in the past it will continue to attract moisture from the atmosphere and therefore needs to be removed and re-done. But why with sand and cement when the DPC was injected from one side only? Forgive me being sceptical but is it because it's this mix with additive, rather than the DPC, that wil stop damp showing on the inside
I've used bonding a few times in the past and didn't make too bad a job of it so am going to have a crack at this. I've used sand and cement too in the past but not for plastering or rendering, only as a mortar for brickwork. What worries me is that sand and cement mix is so much less workable than bonding and I'm unsure of a few things.
Will I need to PVA the wall just like if I was using bonding?
I assume I'll need two coats as it will be about 15 - 20mm thick in total so half on first coat, wait to harden a bit, scratch and apply second coat?
How much sand and cement will I need for about 10m square worth of render?
I can get the additive from the company who installed the DPC and although I figure I could get it cheaper elsewhere it at least means there is less argument in the case of the DPC failing.
Any tips or advice gratefully recieved. Thanks.
EDIT: Just found the render estimator in the building section. According to that I need about 3 bags of cement and 12 bags of sand. Sound right?
The other thing I was thinking is that if I'm not supposed to PVA the wall then do I just wet it down before rendering?
Been lurking for a while picking up some useful advice and just registered.
Bought a house which was in need of a fair bit of work but didn't have much money so have been slowly doing what I can myself (hence the username because I must be Barking Mad to have taken this on!). Before I bought the house the previous owner had a chemical DPC installed along one wall of the house which had been suffering from rising damp. This was injected from the outside only as it's a solid wall but the plaster on the inside remains and will need to be removed and replastered.
I contacted the company who did the DPC and they advise that the bottom metre of plaster needs to come off and be replastered with a 3:1 sand/cement mix with a salt retardand additive. Now my understanding is that where plaster has suffered from damp in the past it will continue to attract moisture from the atmosphere and therefore needs to be removed and re-done. But why with sand and cement when the DPC was injected from one side only? Forgive me being sceptical but is it because it's this mix with additive, rather than the DPC, that wil stop damp showing on the inside
I've used bonding a few times in the past and didn't make too bad a job of it so am going to have a crack at this. I've used sand and cement too in the past but not for plastering or rendering, only as a mortar for brickwork. What worries me is that sand and cement mix is so much less workable than bonding and I'm unsure of a few things.
Will I need to PVA the wall just like if I was using bonding?
I assume I'll need two coats as it will be about 15 - 20mm thick in total so half on first coat, wait to harden a bit, scratch and apply second coat?
How much sand and cement will I need for about 10m square worth of render?
I can get the additive from the company who installed the DPC and although I figure I could get it cheaper elsewhere it at least means there is less argument in the case of the DPC failing.
Any tips or advice gratefully recieved. Thanks.
EDIT: Just found the render estimator in the building section. According to that I need about 3 bags of cement and 12 bags of sand. Sound right?
The other thing I was thinking is that if I'm not supposed to PVA the wall then do I just wet it down before rendering?