extension built around corner of existing kitchen. removed and rerouted soil stack which was on now remove old external corner.cold main entered in same corner.once wall was removed i needed to redirect cold main along where the old external wall below floor finish height.main was entering property in unsleeved and unprotected 15mm copper.was told by builder to leave as , and just extend it.i installed 22mm speed fit to a 22mm stop tap.customer now says they want it done in copper or alcathene.what views on pros and cons on usage of these materials do the lads on here have.it will be below a 2inch screed.