Concrete Drying Conditions

Joined
5 Nov 2008
Messages
560
Reaction score
20
Country
United Kingdom
My foundation trench was filled today (by builders) with C30 mix concrete the depth filled was 1200mm.
How long does this normally take to dry and how long is it normally left before it can be built on?

They have covered the concrete up with sheets of ply wood, are there any precautions to take with regards to the weather its going to be hot tomorrow 25degrees.

Many thanks
 
Sponsored Links
Builders are back Monday afternoon or Tuesday to start the building.
(depending on the Travis delivery slot)
 
takes 28 days to reach its designed strength, but build on the next day when it is nice and green
 
Sponsored Links
You will be able to build on it within 24 hours.

The highest you could possibly build is up to dpc in any case. At 1.2m thick, the concrete will hardly feel it. The percentage of masonry loading against the massive amount of concrete will tell you this.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top