I've received full planning permission to dig out half of my front garden and create a driveway.
The distance from the public footpath to the house is approximately 10 meters. So at half way (5 meters from footpath, 5 meters from house) I need to construct a retaining wall, at this point I will need to excavate approximately 1 meter deep (plus another 0.5 to 1 meter deeper for the footings). I'll be hiring a structural engineer nearer the time to get these measurements right.
I've never done a project this big so I'll be going very slowly, and therefore intend to buy a used micro digger and resell later, rather than hire one.
What I'm unclear about is regarding the risk of seismic movement while I dig out for the retaining wall and footings, then lay the concrete and start building the retaining wall - because I can't imagine completing all that very quickly.
Can I dig out the whole driveway (from public footpath to retaining wall) and then dig the footings and build the retaining wall (this method will give better access for using the digger) or is it essential just to dig a deep narrow trench for the footings and retaining wall, then construct all this before digging out the rest of the driveway?
Can this project be done in any weather conditions or should winter be avoided?
How do I know how much time I have from digging out to completing the retaining wall?
The distance from the public footpath to the house is approximately 10 meters. So at half way (5 meters from footpath, 5 meters from house) I need to construct a retaining wall, at this point I will need to excavate approximately 1 meter deep (plus another 0.5 to 1 meter deeper for the footings). I'll be hiring a structural engineer nearer the time to get these measurements right.
I've never done a project this big so I'll be going very slowly, and therefore intend to buy a used micro digger and resell later, rather than hire one.
What I'm unclear about is regarding the risk of seismic movement while I dig out for the retaining wall and footings, then lay the concrete and start building the retaining wall - because I can't imagine completing all that very quickly.
Can I dig out the whole driveway (from public footpath to retaining wall) and then dig the footings and build the retaining wall (this method will give better access for using the digger) or is it essential just to dig a deep narrow trench for the footings and retaining wall, then construct all this before digging out the rest of the driveway?
Can this project be done in any weather conditions or should winter be avoided?
How do I know how much time I have from digging out to completing the retaining wall?