Hi,
I'm fitting a ledger board to gable end to hang a suspended floor off in new extension. The other end of joists will be on joist hangers hung from the blocks at other end.
Should I bring the dpm up from under the concrete oversight and behind the ledger board at one side and the joist hangers at the other?
Seems to me this would completely eliminate any risk of damp wood.
Thanks