hi very difficult to get cement to site, thinking mixing on site, but concerned using 85 litre hire mixer will take for ever for 4-4.5 m3,also i take it mix fairly runny to help level? cheers
 
is this for an extension?

most builders would use a concrete pump for hard to reach sites these days -some companies have a concrete mixer with pump attached -yes its expensive but the extra say £300 or so is worth it

a pump can usually do a run upto about 100 metres




from memory a 2 guy team can mix a cubic metre of concrete by hand in around an hour, maybe 40 minutes if they push it. no builder would consider doing a 4.5 metre cube by hand
 
cheers no just low walls in garden but very long some 40 metres in total, ive got a minimix company coming, but first comment was wanted to charge 170 a metre, but mine are mostly only 300 by 300 footings so as say about 4-4.5 cubic metres, also needs to do steps up small steep bank approx 900mm any advice?
 
i wondered if mis heard and 170 cubic meter?

I suspect you did. They won't care how you want to spread it, charges are always volumetric, probably with a minimum charge (3 cubic metres seems common)
 

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top