Am worried I may have made a wrong choice when dealing with my Architectural Consultant regarding my foundations.
Firstly the job: Double storey rear extension to rear of a late 80's or 1990 built house. (Tarmac Homes), in place of existing conservatory. Footprint of extension approx 4m x 5m.
Clay soil. Mature Oak to front, 15 is metres from site. Eucalyptus to rear in neighbour's garden. About 8 metres from site.
Sewer (serves us only) runs 500mm below ground level across the site.
Existing house is built on a 250mm engineered slab foundation.
Had 1 set of BR drawigns approved by BC with 1.5 - 2.5 trench foundations, with B&B floor on top.
After changing design and getting plans drawn up by a new designer, they specified standard 1.3m deep. After I reminded them about proximity of Eucalyptus and told them that the existing house was built on an engineered slab, they are now talking about getting a S.E to design a Piled Raft foundation.
They have informed me that foundation types cannot be mixed - ie, as the existing house is piled raft (are all rafts piled? because all I have told them is that there is a raft- they may have spoken to BC though) Is the above point correct? If so, why did BC approve the last set of drawings, when they knew that the existing was a raft type foundation?
What I don't want to do is under-spec things, as we hope to be here a long time. I also don't want any nasty surprises during the build process, so want to budget before I start rather than digging the garden up and realising it is all too costly.
Architectural Consultant has quoted about £325 for the design of a piled raft (by his S.E) and told us it is likely to be about 1.5 times the cost of regular foundations.
He seems very reluctant to resubmit the previously approved design which had the Block and Beam floor- mainly because to allow the 300mm cavity below, we would start encroaching on the drain which is 500mm down.
Any general advice? I have already authorised the SE to design the raft, but just wanted to check I wasn't making a huge mistake- would rather write £325 off now if I will save £'000's.
Firstly the job: Double storey rear extension to rear of a late 80's or 1990 built house. (Tarmac Homes), in place of existing conservatory. Footprint of extension approx 4m x 5m.
Clay soil. Mature Oak to front, 15 is metres from site. Eucalyptus to rear in neighbour's garden. About 8 metres from site.
Sewer (serves us only) runs 500mm below ground level across the site.
Existing house is built on a 250mm engineered slab foundation.
Had 1 set of BR drawigns approved by BC with 1.5 - 2.5 trench foundations, with B&B floor on top.
After changing design and getting plans drawn up by a new designer, they specified standard 1.3m deep. After I reminded them about proximity of Eucalyptus and told them that the existing house was built on an engineered slab, they are now talking about getting a S.E to design a Piled Raft foundation.
They have informed me that foundation types cannot be mixed - ie, as the existing house is piled raft (are all rafts piled? because all I have told them is that there is a raft- they may have spoken to BC though) Is the above point correct? If so, why did BC approve the last set of drawings, when they knew that the existing was a raft type foundation?
What I don't want to do is under-spec things, as we hope to be here a long time. I also don't want any nasty surprises during the build process, so want to budget before I start rather than digging the garden up and realising it is all too costly.
Architectural Consultant has quoted about £325 for the design of a piled raft (by his S.E) and told us it is likely to be about 1.5 times the cost of regular foundations.
He seems very reluctant to resubmit the previously approved design which had the Block and Beam floor- mainly because to allow the 300mm cavity below, we would start encroaching on the drain which is 500mm down.
Any general advice? I have already authorised the SE to design the raft, but just wanted to check I wasn't making a huge mistake- would rather write £325 off now if I will save £'000's.