I recently poured the concrete into my 1m footings for a 2storey extension. i only put in about 500mm as i was limited by my foul drain pipe (cannot be moved unfortunately).
there is a slight fall in the level of the concrete, about 1.5inches over the the 5m length. the correct/high the drain end. i've layed 1 block either side of the drain and have a conc lintel to go over.
my question is, can i now pour 9-10inches of concrete over the rest of the footings (level this time) and begin blocking up from there?
if so do i need to reinforce, or can i simply lay on top of, i worry whether it may crack or something?
any help will be greatly appreciated - stressing out about what to do
there is a slight fall in the level of the concrete, about 1.5inches over the the 5m length. the correct/high the drain end. i've layed 1 block either side of the drain and have a conc lintel to go over.
my question is, can i now pour 9-10inches of concrete over the rest of the footings (level this time) and begin blocking up from there?
if so do i need to reinforce, or can i simply lay on top of, i worry whether it may crack or something?
any help will be greatly appreciated - stressing out about what to do