Im looking advice from other builders with vast experience. Ive been working in the building trade over 20 years working for all different trades and have experience on building garages, renovations on day work, pricing small jobs for myself.
Ive built garages on my own along with a labourer but as mentioned, only day work. Im a sole trader whos always provided labor only with the clients always providing materials. Now im going to start building and providing everything. What sort of profits should i be adding on top of all labor and material costs.
Ill also be registering for vat. I live in Ireland where the vat threshold is 37.5k and once you go over this, one has to charge vat. Below is what ive priced for a garage ill be advertising in the summer. Its for garages one can build here without planning permission.
Itll be for a 5x5m garage with a trussed roof! Below is what i have it priced at. My pricing is without pricing any profit, insurances and unforeseen costs, only labor and materials.
Ive just covered from the ground up including the pour of footings. No ground works priced in because of all the different ground conditions there is. I would only price once i know what ive to be digging/working with underground.
Concrete pour and steel mesh!
Day1 Installing steel mesh plus concrete pour 1+1 men, 320euro (concrete lorry being able to pull up beside the trench or small distance with the wheel barrow)
Block footings!
Day2, Setting out block and laying. 2+1 men 500euro
Day3, Scraping , filling inside the footings for levels with hardcore stones
1+1men 300euro. Digger hire 150euro, dumper hire 100euro, roller hire 100euro (total 650e)
Day4, finish off filling with sand for levels. Lay heavy guage with plastic risers for steel mesh, steel mesh. 1+1 men 300 euro, digger, dumper,roller hire 350 (total 650e)
Day5, Concrete pour 2+1 men 500euro
Day6, extra day just incase 1 man 200euro (total 3250)
Materials.
25 linear m x 0.900 wide x .300 deep = 6.75cm . 7mc 560euro
8-10 ton 804 stone 100euro
3-4ton sand 100 euro
heavy guage DPC roll 30 euro
6 sheets of 4.8x2.4 steel mesh 10mm 375euro
steel hychairs 75 euro
steel wire 10e
Possible 5 ton extra 804 50e
plastic risers for under mesh 50e (total 1425e)
50x4 4 inch blocks = 200 block x 0.60c a block 120euro
sand and cement for footings 100euro (probably over estimated)
Wall ties for all block 70-100e
4inch dpc 10e
soap bars and concrete brick 50e
Concrete bull float hire 40e (Total 420e)
Day7 - Block laying( though opes and gables sq. estimate.
61 block long x 15 high = 912 x 2 = 1830 block
Peaks 12.1 block long x 7 high = 85 x 4 = 340.
2170 blocks @ 60c each is 1302euro
sand 10 ton 200euro
cement 40 bags @ 5.50each 220euro (probably over estimate)
wall ties see previous
lintels, cill 100euro
dpc 30euro
soapbars , concrete brick 90e (total 1942euro)
Block laying rates here are 1.25e-1.50e per block through opes.
2170x1.50e = (3255 total)
Roof. This is where i could be a day or two over estimate or hit it on the money.
Materials.
9 sissor roof trusses 540euro
wall plate 35e
wall plate straps 30e
truss bracing 150m x 4x1 120e
20kg nails 70euro (might need another box)
roof window 200e
truss brackets 15e
twisted nails 25e
2 rolls breathable felt 120e
18sqm roof slates 600x300 400 slates. ( my estimate could be out by some here) 400e
32 lengths 2x2 battens 4.8m 16ft 132e
11 ridge tiles + ridge nails 115e
4x2 treated timber for dry verdge (express nailed onto outer black to take batten) 40e
express nails 8e
wall straps 60e
ridge 6 lengths 93e
expandig mesh 8x2 7 off. 50e
slate hooks 50e (500)
6mm ply 13e
over fascia vent 40e
9x1 teated 33e
fascia nails+corners 35e (total 2340euro)
Day1 wall plate, unload trusses, timber on top of gable 2 men 400e
day2, errect trusses , ridge trim onto the 4x2s 3 men 450e
day3, brace trusses, 9x1 on front and back, fascia vent 2 men 400e (day 3 and 4 for both trusses and bracing but put down separate days for them pricing)
day4, felt , battens 1+1 men 300euro
day5, felt battens plus roof window 1+1 300euro
day6 slate one side 1+1 300e
day7, slate other side plus around window 1+1 300e
day8 ridge slates, fascia 1+1 300e (total 2750e)
1 window 250e
1 door 800e
1 roller door 1000e (total 2050)
Rendering
Day1 scratch coat 2+1 men 500euro
Day2, reveals and plinth 1+1 300e
Day3, Float one gable plus 1 side 2+1 men 500e
Day4, Float one gable and one side 2+1 men 500e
day5, for extra just incase 1 man 200e (Total 2000)
materials
2x1 battens for reveals,plinth 13 16fts 30euro
masonry nails 8e
sand 7 ton 140e
plasterciser/waterproofer 50e
cement 30-36 bags(probably over estimate) 200e
Large mixer hire 100e (total 530euro_)
Scaffolding 1500euro (have own)
Total is 21462euro
Ive built garages on my own along with a labourer but as mentioned, only day work. Im a sole trader whos always provided labor only with the clients always providing materials. Now im going to start building and providing everything. What sort of profits should i be adding on top of all labor and material costs.
Ill also be registering for vat. I live in Ireland where the vat threshold is 37.5k and once you go over this, one has to charge vat. Below is what ive priced for a garage ill be advertising in the summer. Its for garages one can build here without planning permission.
Itll be for a 5x5m garage with a trussed roof! Below is what i have it priced at. My pricing is without pricing any profit, insurances and unforeseen costs, only labor and materials.
Ive just covered from the ground up including the pour of footings. No ground works priced in because of all the different ground conditions there is. I would only price once i know what ive to be digging/working with underground.
Concrete pour and steel mesh!
Day1 Installing steel mesh plus concrete pour 1+1 men, 320euro (concrete lorry being able to pull up beside the trench or small distance with the wheel barrow)
Block footings!
Day2, Setting out block and laying. 2+1 men 500euro
Day3, Scraping , filling inside the footings for levels with hardcore stones
1+1men 300euro. Digger hire 150euro, dumper hire 100euro, roller hire 100euro (total 650e)
Day4, finish off filling with sand for levels. Lay heavy guage with plastic risers for steel mesh, steel mesh. 1+1 men 300 euro, digger, dumper,roller hire 350 (total 650e)
Day5, Concrete pour 2+1 men 500euro
Day6, extra day just incase 1 man 200euro (total 3250)
Materials.
25 linear m x 0.900 wide x .300 deep = 6.75cm . 7mc 560euro
8-10 ton 804 stone 100euro
3-4ton sand 100 euro
heavy guage DPC roll 30 euro
6 sheets of 4.8x2.4 steel mesh 10mm 375euro
steel hychairs 75 euro
steel wire 10e
Possible 5 ton extra 804 50e
plastic risers for under mesh 50e (total 1425e)
50x4 4 inch blocks = 200 block x 0.60c a block 120euro
sand and cement for footings 100euro (probably over estimated)
Wall ties for all block 70-100e
4inch dpc 10e
soap bars and concrete brick 50e
Concrete bull float hire 40e (Total 420e)
Day7 - Block laying( though opes and gables sq. estimate.
61 block long x 15 high = 912 x 2 = 1830 block
Peaks 12.1 block long x 7 high = 85 x 4 = 340.
2170 blocks @ 60c each is 1302euro
sand 10 ton 200euro
cement 40 bags @ 5.50each 220euro (probably over estimate)
wall ties see previous
lintels, cill 100euro
dpc 30euro
soapbars , concrete brick 90e (total 1942euro)
Block laying rates here are 1.25e-1.50e per block through opes.
2170x1.50e = (3255 total)
Roof. This is where i could be a day or two over estimate or hit it on the money.
Materials.
9 sissor roof trusses 540euro
wall plate 35e
wall plate straps 30e
truss bracing 150m x 4x1 120e
20kg nails 70euro (might need another box)
roof window 200e
truss brackets 15e
twisted nails 25e
2 rolls breathable felt 120e
18sqm roof slates 600x300 400 slates. ( my estimate could be out by some here) 400e
32 lengths 2x2 battens 4.8m 16ft 132e
11 ridge tiles + ridge nails 115e
4x2 treated timber for dry verdge (express nailed onto outer black to take batten) 40e
express nails 8e
wall straps 60e
ridge 6 lengths 93e
expandig mesh 8x2 7 off. 50e
slate hooks 50e (500)
6mm ply 13e
over fascia vent 40e
9x1 teated 33e
fascia nails+corners 35e (total 2340euro)
Day1 wall plate, unload trusses, timber on top of gable 2 men 400e
day2, errect trusses , ridge trim onto the 4x2s 3 men 450e
day3, brace trusses, 9x1 on front and back, fascia vent 2 men 400e (day 3 and 4 for both trusses and bracing but put down separate days for them pricing)
day4, felt , battens 1+1 men 300euro
day5, felt battens plus roof window 1+1 300euro
day6 slate one side 1+1 300e
day7, slate other side plus around window 1+1 300e
day8 ridge slates, fascia 1+1 300e (total 2750e)
1 window 250e
1 door 800e
1 roller door 1000e (total 2050)
Rendering
Day1 scratch coat 2+1 men 500euro
Day2, reveals and plinth 1+1 300e
Day3, Float one gable plus 1 side 2+1 men 500e
Day4, Float one gable and one side 2+1 men 500e
day5, for extra just incase 1 man 200e (Total 2000)
materials
2x1 battens for reveals,plinth 13 16fts 30euro
masonry nails 8e
sand 7 ton 140e
plasterciser/waterproofer 50e
cement 30-36 bags(probably over estimate) 200e
Large mixer hire 100e (total 530euro_)
Scaffolding 1500euro (have own)
Total is 21462euro