We ran some cables under a lorry hard standing a few years back as it was constructed.
If was originally a field, and the contractors dug us a 600mm trench, which then had a few 6" ducts chucked in on top of our cables for the future.
The trench was backfilled, and they then spread large rocks, finer rocks, finer rocks still and then dusty stuff, all rollered down. Reinforced concrete was then poured in sections.
A couple years later when we had to get to the ends of our ducts to add some cables, we had to excavate down to just under 1.5m to get to our ducts!
If was originally a field, and the contractors dug us a 600mm trench, which then had a few 6" ducts chucked in on top of our cables for the future.
The trench was backfilled, and they then spread large rocks, finer rocks, finer rocks still and then dusty stuff, all rollered down. Reinforced concrete was then poured in sections.
A couple years later when we had to get to the ends of our ducts to add some cables, we had to excavate down to just under 1.5m to get to our ducts!