So we had our appointed plasterer/screeder screed our Polypipe underfloor heated floor in our new extension on Friday and despite asking time again about how he would check the levels and requesting that he leave a clearance of 35mm below the threshold of our bifold doors, he has messed up.
Though on one end of the doors, the clearance is approximately 35mm, it narrows to 28mm near the middle and back to 31mm at the other end. This is unsatisfactory because it does not leave sufficient space for our stone slab flooring. I am majorly ****ed off because I made it abundantly clear that they had to leave 35mm under the rim of the threshold.
My question is, can anything be done. He has suggested hiring a grinder (at his expense) to correct his mistake but won't that just end up damaging the ufh pipes?
Though on one end of the doors, the clearance is approximately 35mm, it narrows to 28mm near the middle and back to 31mm at the other end. This is unsatisfactory because it does not leave sufficient space for our stone slab flooring. I am majorly ****ed off because I made it abundantly clear that they had to leave 35mm under the rim of the threshold.
My question is, can anything be done. He has suggested hiring a grinder (at his expense) to correct his mistake but won't that just end up damaging the ufh pipes?