Hi
I have just moved into a new build property which requires the construction of a large patio, approx. 65m2. As we are moving near to a slate mining area in North Wales I have got the notion to be sympathetic to the surrounding area and use an external slate floor tile of approx. 10mm thickness from one of the local quarries. Obviously with a tile of this thickness, a solid and well thought out sub base will be required. I was thinking that a 100mm sub-base of compacted granular material based on ground conditions followed by 100mm of poured concrete, most likely in 2 – 3 separate pours to allow the construction of joints in the slab.
Does this sound like a reasonable plan?
I guess my main questions are as follows:
Would a 4-2-1 concrete mix be acceptable in this application or should I go weaker or stronger?
The largest single pour will be approx. 36 m2 (4 x 9 m) should I consider the inclusion of re-bar mesh or would a fibrous concrete be sufficient? Should I perhaps split this into 2 separate pours and add an extra joint?
That leads me onto my next question, do I go with a joggle joint or do I use a dowelled joint with one end de-bonded and Flexcell in between. Is one preferred over the other?
Finally, what is the consensus on a DPM, I see the pro’s and con’s for its inclusion. The problem I have is I can’t figure out what to do with the excess beyond the perimeter of the slab. My lawn will essential butt up to the edge of the concrete slab, should I just fold back the DPM on itself and trim to the height of the slab. How would I prevent water getting between the DPM and the slab and migrating underneath the slab?
Look forward to hearing your thoughts.
Cheers
Matt
I have just moved into a new build property which requires the construction of a large patio, approx. 65m2. As we are moving near to a slate mining area in North Wales I have got the notion to be sympathetic to the surrounding area and use an external slate floor tile of approx. 10mm thickness from one of the local quarries. Obviously with a tile of this thickness, a solid and well thought out sub base will be required. I was thinking that a 100mm sub-base of compacted granular material based on ground conditions followed by 100mm of poured concrete, most likely in 2 – 3 separate pours to allow the construction of joints in the slab.
Does this sound like a reasonable plan?
I guess my main questions are as follows:
Would a 4-2-1 concrete mix be acceptable in this application or should I go weaker or stronger?
The largest single pour will be approx. 36 m2 (4 x 9 m) should I consider the inclusion of re-bar mesh or would a fibrous concrete be sufficient? Should I perhaps split this into 2 separate pours and add an extra joint?
That leads me onto my next question, do I go with a joggle joint or do I use a dowelled joint with one end de-bonded and Flexcell in between. Is one preferred over the other?
Finally, what is the consensus on a DPM, I see the pro’s and con’s for its inclusion. The problem I have is I can’t figure out what to do with the excess beyond the perimeter of the slab. My lawn will essential butt up to the edge of the concrete slab, should I just fold back the DPM on itself and trim to the height of the slab. How would I prevent water getting between the DPM and the slab and migrating underneath the slab?
Look forward to hearing your thoughts.
Cheers
Matt