Hi All
Just a little advice please.
At the front of my house is my electric cupboard in my living room. At present there is my main Consumer Unit and a 2nd one. This used to be for storage heaters before i mived in, so it is now redundant.
What i would like to have is 2 or 3 external weatherproof sockets (1 on the front of my house and 2 on the back), just to run things like a mower, perhaps a water feature. Thats about it.
I am currently digging a small drainage channel around the house as the previous occupant had built the concrete drive above my DPC in places. I thought it would be a good opportunity to run cable from the front of the house to the back ready for the sockets.
I can drill straight through the wall, bury the cable in the small trench and then get a sparky to connect to my unused C.U etc.
I know someone who signs off others work if done properly of course!
So, can i use SWA 4mm cable for this?
Do i have to bury very far down as i am struggling to get further than about 100mm? The trench will be filled with decorative stone to aid in water drainage so the cable will not be visible or moved again.
Am i missing anything? I know that Part P means i need it signing off etc, even though i have no intention of moving house (not that that is the only reason why we do get things signed off of course), but i just want to keep the manual labour costs down and be prepared for him.
Any advice would be greatly appreciated.
Just a little advice please.
At the front of my house is my electric cupboard in my living room. At present there is my main Consumer Unit and a 2nd one. This used to be for storage heaters before i mived in, so it is now redundant.
What i would like to have is 2 or 3 external weatherproof sockets (1 on the front of my house and 2 on the back), just to run things like a mower, perhaps a water feature. Thats about it.
I am currently digging a small drainage channel around the house as the previous occupant had built the concrete drive above my DPC in places. I thought it would be a good opportunity to run cable from the front of the house to the back ready for the sockets.
I can drill straight through the wall, bury the cable in the small trench and then get a sparky to connect to my unused C.U etc.
I know someone who signs off others work if done properly of course!
So, can i use SWA 4mm cable for this?
Do i have to bury very far down as i am struggling to get further than about 100mm? The trench will be filled with decorative stone to aid in water drainage so the cable will not be visible or moved again.
Am i missing anything? I know that Part P means i need it signing off etc, even though i have no intention of moving house (not that that is the only reason why we do get things signed off of course), but i just want to keep the manual labour costs down and be prepared for him.
Any advice would be greatly appreciated.