laying 150mm concrete, will 1 day be enough to allow to go off before walking on it?
 
It'll be firm enough to stand or walk on but will still be very green and so will be fragile and easily broken at the edges if they are unsupported.
 
eventually to insulate with 90mm celotex, install underfloor heating then screed with a wooden floor finish.
 
I seem to recall some rule of thumb that says something like a month an inch before laying a timber floor on top. You'll have a huge amount of water in that slab that with the DPC in place can only escape upwards.
There's a poster on here called woodulike (or something similiar) who seems to be something of an engineered floor guru, I think it's his living, hopefully he may give a definate answer.
 
yes thanks, it was really at this stage to know how long before walking traffic can go on the concrete after laying. the finished floor will be 3 mths away at least.
 
the answers above relate to how long you should leave the concrete until you could tile on it, which you are not going to do. However the slab is going to continue tb shed this water whatever happens and I'm not sure what the result would be if you put impervious insualtion on top followed by a screed before it was dry.

By the way, when you lay the screed, you will also have a long drying-time. The different "rules of thumb" are :

1) One day per mm
2) One week per cm
3)One month per inch

Bit of variation there as you can see.

By the way are you really pushed for time to do this, or just surprised at the length of drying-time ?
 
hi, in no rush, just surprised at drying time, if it takes 6mth or longer id rather wait and do it right., plenty of other jobs to do.
 
A site agent I have worked with in the past had an oak floor laid on top of green screed a couple of years ago, time constraints and a rush to get the job done but ultimately the boards ended up looking like some sort of corrugated floor and had to all be ripped up :oops: still every cloud and all that- there were several oak fuelled warm houses that winter :wink:
 

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top