Hi all
Ready to sort the DPM and DPC, was going to put the inner DPC under the DPM and run it down the blockwork 100mm so the DPM laps over it for width of block. The DPM has the concrete slab laid ready for insulation and screed. But have seen that it has been suggsted for the DPM to go underneath the DPC.
Which is best and right?!
Sorry another qu.
Ready to sort the DPM and DPC, was going to put the inner DPC under the DPM and run it down the blockwork 100mm so the DPM laps over it for width of block. The DPM has the concrete slab laid ready for insulation and screed. But have seen that it has been suggsted for the DPM to go underneath the DPC.
Which is best and right?!
Sorry another qu.