Hi all,
just received the first draft footing drawings from teh architect and the following comment was on the drawing:-
Eccentrically loaded foundations700x700 trench fill to a depth of1000mm below new ground level subject to site inspection and
approval of BCO
New foundation required for new internal wall Trench foundation along side the existing foundation and to be approved on site by BCO.
( Typical trench foundation would be 600 x 800 concrete to a depth of 1000mm depending on site conditions )
What exactly is the depth of the footings he is recommending here?
Thanks
Andy
just received the first draft footing drawings from teh architect and the following comment was on the drawing:-
Eccentrically loaded foundations700x700 trench fill to a depth of1000mm below new ground level subject to site inspection and
approval of BCO
New foundation required for new internal wall Trench foundation along side the existing foundation and to be approved on site by BCO.
( Typical trench foundation would be 600 x 800 concrete to a depth of 1000mm depending on site conditions )
What exactly is the depth of the footings he is recommending here?
Thanks
Andy