how can we Support neighbouring patio and sun lounge as our footings are deeper

Hello

Help required again please.

The neighbour strikes back. I sent them a party wall notice to remove the chimney from the wall. With a few one options sent by the surveyor was 1. Consent to all work mentioned.

2. Consent to the work subject to schedule of conditions report for her property paid by us.

3. Dissent to every thing.

4. Appoint their surveyor.

The neighbour has signed the consent option 2 (subject to we paying for the survey of her property and she receiving the report) which we do not have any problems.

She has also sent an accompanying letter that she is OK subject to we doing a schedule of condition on our property and sending her the report and the photos.(this is bizarre because we are going to demolish our chimney etc... and what is the schedule of condition for our property going to achieve for her?)

Also as per party wall act, is this a mandatory or legally required to provide a schedule of conditions for our property before we commence the works.

Thanks

LK
 
Sponsored Links

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top