I know that central heating systems will often have drops and rises, as they fall to go under floor then rise to go to taps, etc and that overall pressure is measured from bottom of tank (gravity sys) to spout of tap.
But is it bad practice for a run of pipe to have more up/downs than necessary?
Originally I had bath, WC & basin on one wall, so I had two 22mm feeds to bath, two 15mm to basin and one to WC, all as normal.
As we are moving basin to another wall I was just going to re-route the original feeds to basin to the adjacent wall.
However, now I've got the boards up, it's sods law that there are a few pipes all very close together and the ones I need to cut into and put a new T into are right at the back up against the wall, and look awkward for either soldering or compression joints.
So, the cold feed is close enough to new WC position for that to be left as is, but the hot feed, would it be OK use existing rise, put an elbow on it and take it further along wall where it is easier to make a connection, then take it under floor to new basin position, then back up to taps as normal?
As I have the bath & toilet waste both running across this wall it will be boxed in so clipping it along the wall before going under floor again will not be seen.
But is it considered bad practice to run it this way?
Might sound silly to those in the know but I thought I'd ask!
But is it bad practice for a run of pipe to have more up/downs than necessary?
Originally I had bath, WC & basin on one wall, so I had two 22mm feeds to bath, two 15mm to basin and one to WC, all as normal.
As we are moving basin to another wall I was just going to re-route the original feeds to basin to the adjacent wall.
However, now I've got the boards up, it's sods law that there are a few pipes all very close together and the ones I need to cut into and put a new T into are right at the back up against the wall, and look awkward for either soldering or compression joints.
So, the cold feed is close enough to new WC position for that to be left as is, but the hot feed, would it be OK use existing rise, put an elbow on it and take it further along wall where it is easier to make a connection, then take it under floor to new basin position, then back up to taps as normal?
As I have the bath & toilet waste both running across this wall it will be boxed in so clipping it along the wall before going under floor again will not be seen.
But is it considered bad practice to run it this way?
Might sound silly to those in the know but I thought I'd ask!