Hi,

What is process to register new meter ofgem approve to supplier, if fitted to new building on dead supply ?
 
Sponsored Links
I do not understand what you are trying to do here.

Ofgem approve? What is that?

For a new building you apply to the DNO for a supply and sign a supply contract. The DNO provides the supply and the meter.

You are responsible for the provision of the consumer unit/ distribution board and all wiring after that.
 
Nope, doesn't work like that. The only people who can provide you with a meter is the MOP who work on behalf of the electricity supplier (not the DNO).

To get a meter you will need to contact the electricity supplier of your choice, and the will arrange for the meter to be installed for you.
 
Sponsored Links
those meters are intended for landlords wishing to sub-meter electricity to tenants, etc.

For a new connection to the public supply you will need to do as others have said to get a connection and meter.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top