I've got a house which has/needs lots of renovation on it.
These are the things I still need to get done, but in particular relation to the 2 plumbing works and plastering, I'm a but unsure about the best way of doing things. I'm sure if I asked the plasterer he'd say it would be better to do his bit first, and vice-versa for the plumber! lol
At the back of my terrace house I have a kitchen, and on top of it a bathroom. The ceiling in both is ripped off/down at the moment.
I need the following done: -
Can anyone help/advise me with regard to the best route.....?
Thanks,
David
These are the things I still need to get done, but in particular relation to the 2 plumbing works and plastering, I'm a but unsure about the best way of doing things. I'm sure if I asked the plasterer he'd say it would be better to do his bit first, and vice-versa for the plumber! lol
At the back of my terrace house I have a kitchen, and on top of it a bathroom. The ceiling in both is ripped off/down at the moment.
I need the following done: -
- Re-board kitchen ceiling
Skim kitchen ceiling
Re-skim kitchen walls
Re-board bathroom ceiling
Skim bathroom ceiling
Re-plaster whole of bathroom (plaster has been ripped off the walls as it was old and crumbling) - Should this be done before some plumbing has been put in place for the new bathroom/shower?)
New combi boiler fitted on wall in kitchen (old tank/backboiler ripped out elsewhere) - I expect pipes from the new boiler having to go through the kitchen ceiling (the one that needs re-boarding & skimming)
Need new bathroom fitted - I expect this would be lots easier if the ceiling hasn't yet gone back up in the kitchen below it yet?
Bathroom Tiling
Can anyone help/advise me with regard to the best route.....?
Thanks,
David