Hi
I'm moving the WC in our bathroom which is on the ground floor. The soil pipe currently drops vertically about 850mm to the bottom of the crawl space under the floor where it is connected to a 90 deg bend taking the waste outside.
The new toilet outlet will be approx 2m away from the existing outlet. Am I better to run the new soil pipe from the WC to the existing 90 deg bend (ie at about 25 deg) or am I better to have a slight fall from the WC outlet until it is over the 90 deg bend and then drop vertically?
If its the latter what is the correct fall? I think I read somewhere else on the forum 1 in 40 is right?
Thanks
F
I'm moving the WC in our bathroom which is on the ground floor. The soil pipe currently drops vertically about 850mm to the bottom of the crawl space under the floor where it is connected to a 90 deg bend taking the waste outside.
The new toilet outlet will be approx 2m away from the existing outlet. Am I better to run the new soil pipe from the WC to the existing 90 deg bend (ie at about 25 deg) or am I better to have a slight fall from the WC outlet until it is over the 90 deg bend and then drop vertically?
If its the latter what is the correct fall? I think I read somewhere else on the forum 1 in 40 is right?
Thanks
F