Guys,
Digging foundation, recommended by BCO to go 1M deep, 600mm wide and the footings work out to 11m in length, in all 7 cubic metres of area to fill.
Question is what is the most cost effective method I can use?
1: Do a complete fill of the footings, working out to approx £550
2: Do a partial fill (approx 350mm as per BCO) and carry on up to dpc with the relevant blocks.
Thoughts appreciated.
Thanks
Digging foundation, recommended by BCO to go 1M deep, 600mm wide and the footings work out to 11m in length, in all 7 cubic metres of area to fill.
Question is what is the most cost effective method I can use?
1: Do a complete fill of the footings, working out to approx £550
2: Do a partial fill (approx 350mm as per BCO) and carry on up to dpc with the relevant blocks.
Thoughts appreciated.
Thanks