We contracted a builder to do large extension and to renovate the existing house. The project lasted almost a year and we made every payment on time. We have now come to a stalemate with the builder over a small completion payment.
The project has not been completed as there is some skirting to fit and decorate and a radiator to fit. There are also two large piles of spoil from the groundworks and some significant damage to a parking area that needs repairing. We have also not had the completion certificate from the building inspector of the FENSA certificate for the windows.
There is also a snagging payment due but so far no snagging has been completed.
The builders have also left a three foot hole outside the back door and have not levelled off the ground around the house. They say this was not in their contract but as it was such a large project the contract was in broad terms ie groundworks and drainage items and fine detail was not listed. The sides of the manholes and drains are also exposed and are not all at the same level.
My questions are 1) is it reasonable to withhold the completion payment until all work is completed and the completion certificate has been issued?
2) if a parking area was damaged (now a foot plus deep hole 5mx10m) should that be repaired or is it normal to damage the ground 30m from the house?
3) with a large build would you normally level the ground outside new doors and around drains so the doors can be safely accessed? We've been told this wouldn't normally be done as part of the groundworks but as landscaping. We cannot currently use the doors are the holes outside them are so deep and the ground is unlevel.
We don't want to be unreasonable and would like to understand what would normally be expected as part of a large build.
The project has not been completed as there is some skirting to fit and decorate and a radiator to fit. There are also two large piles of spoil from the groundworks and some significant damage to a parking area that needs repairing. We have also not had the completion certificate from the building inspector of the FENSA certificate for the windows.
There is also a snagging payment due but so far no snagging has been completed.
The builders have also left a three foot hole outside the back door and have not levelled off the ground around the house. They say this was not in their contract but as it was such a large project the contract was in broad terms ie groundworks and drainage items and fine detail was not listed. The sides of the manholes and drains are also exposed and are not all at the same level.
My questions are 1) is it reasonable to withhold the completion payment until all work is completed and the completion certificate has been issued?
2) if a parking area was damaged (now a foot plus deep hole 5mx10m) should that be repaired or is it normal to damage the ground 30m from the house?
3) with a large build would you normally level the ground outside new doors and around drains so the doors can be safely accessed? We've been told this wouldn't normally be done as part of the groundworks but as landscaping. We cannot currently use the doors are the holes outside them are so deep and the ground is unlevel.
We don't want to be unreasonable and would like to understand what would normally be expected as part of a large build.