Hello everyone,
I am writing ask for advice on starting an extension. Original application for extension was approved in May 2015 and is running for 3 years. Years passed with subsequent further applications which were refused. Finally a few weeks ago we applied for a minor amendment to the original 2015 application and that was granted.
I was told anecdotally that construction is deemed to have started once the foundations are laid down to the dampproof course. If the foundations and DPC are completed before the planning application expiry then we will not miss the deadline. But if we miss the deadline then we will have to re-apply from scratch.
As a result we do not have the time to apply for buildings regs as it's a few weeks before expiry. We have to start digging the foundations now. The inspector will have to be called out twice, once to inspect the trench and once more to inspect the foundations. And once he approves the foundations, then the council considers that the building has commenced and our planning application will not lapse.
Do you agree with the above plan? Have I described the process correctly or am I missing anything?
Many thanks
I am writing ask for advice on starting an extension. Original application for extension was approved in May 2015 and is running for 3 years. Years passed with subsequent further applications which were refused. Finally a few weeks ago we applied for a minor amendment to the original 2015 application and that was granted.
I was told anecdotally that construction is deemed to have started once the foundations are laid down to the dampproof course. If the foundations and DPC are completed before the planning application expiry then we will not miss the deadline. But if we miss the deadline then we will have to re-apply from scratch.
As a result we do not have the time to apply for buildings regs as it's a few weeks before expiry. We have to start digging the foundations now. The inspector will have to be called out twice, once to inspect the trench and once more to inspect the foundations. And once he approves the foundations, then the council considers that the building has commenced and our planning application will not lapse.
Do you agree with the above plan? Have I described the process correctly or am I missing anything?
Many thanks