My extension was supposedly out of level. 50mm over 7m so when the floor was screeding level it falls 30mm below the finished brick opening internally. Outside is 4 courses down as I need to build it up. What are my threshold options. The screed was meant to go to brick level but screeder reckons it would have noticed too much. Will this be an issue? This 30mm internal drop
 
What will be the floor covering internally? tile?
Is the screed not level? makes little sense.
 
So from my back door to the the bi fold opening the screed guy said the build was 50mm out of level. He’s screeded it with a rise of 20mm but said rising 50mm would notice too much. It’s not dry enough to go a put a level on it yet. I will check it tomorrow.
Will be a laminate I should imagine
 

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top