Hello everyone. Brickies coming this week at short notice after another job was called off. Hence a rush to get some gear for him.
(For conservatory)
5 courses up to slab level total run 10.21m. I reckon this means I need 476 bricks with 4.65 bricks per linear metre.
One full height wall 2.1m x 3.5m. Brick on outside, block on inside.
441 bricks and 74 blocks.
What percentage for damages etc. 5%?
How much sand and cement do I need?
Thanks guys.
(For conservatory)
5 courses up to slab level total run 10.21m. I reckon this means I need 476 bricks with 4.65 bricks per linear metre.
One full height wall 2.1m x 3.5m. Brick on outside, block on inside.
441 bricks and 74 blocks.
What percentage for damages etc. 5%?
How much sand and cement do I need?
Thanks guys.