Hi,
If i want to rebuild the outhouse were out outside toilet is and get planning etc can i keep the original drains or do i have to replace them, they were fine for the old toilet and i am happy to leave the toilet were it is, so just wondered if i can just keep them and assume they would only get replaced if i was moving the toilets location etc.
Thanks Lee
 
Sponsored Links
Using existing drainage is fine.

However, don't be surprised if the existing drain position is not in quite the right place or that the original drains interfere with a foundation dig.

In this instance it makes sense to simply re-hash the drains with new stuff including an access chamber if necessary.

building control will need to have a squint also.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Sponsored Links
Back
Top