- Joined
- 29 Aug 2010
- Messages
- 22
- Reaction score
- 0
- Country
I'm intending to lay a concrete floor with water UFH, but I'm reading conflicting advice when it comes to the order??
To me the logical order would be ...
70mm screed with pipe work in and either mesh or fibre reinforce
100mm insulation foam
100mm Slab concrete
DPM
Binding 10mm
Hardcore
This would mean you're just heating the screed layer?.
I've also found however (from the internet and within this forum) the following order suggested...
70mm Screed with pipe work in and either mesh or fibre reinforce.
100mm Slab concrete
100mm Insulation foam
DPM
Binding 10mm
Hardcore
Doesn't this method obviously mean you're heating the large slab too? How would you clip the pipework with this method? drilling and rawlpluggin the slab?
Is either method acceptable? does either method do the job as effectively as the other ?
Or is it a matter of whether there is UFH in the job at all alters which one you use?
Thanks
Daz
To me the logical order would be ...
70mm screed with pipe work in and either mesh or fibre reinforce
100mm insulation foam
100mm Slab concrete
DPM
Binding 10mm
Hardcore
This would mean you're just heating the screed layer?.
I've also found however (from the internet and within this forum) the following order suggested...
70mm Screed with pipe work in and either mesh or fibre reinforce.
100mm Slab concrete
100mm Insulation foam
DPM
Binding 10mm
Hardcore
Doesn't this method obviously mean you're heating the large slab too? How would you clip the pipework with this method? drilling and rawlpluggin the slab?
Is either method acceptable? does either method do the job as effectively as the other ?
Or is it a matter of whether there is UFH in the job at all alters which one you use?
Thanks
Daz