I'm currently having the building work done for a conservatory.
I have a local friend doing the building work and another company is supplying and fitting the conservatory.
Today I asked the conservatory company whether it's a problem putting the screed down after the roof had been fitted as I'm integrating UFH into the screed. He asked about base construction and I told him that the base was going to be mot hardcore, sand, 750mm Kingspan, Ufh, screed. He said it needs a 100mm concrete slab aswell.
I've spoken to my builder, and he seems pretty adamant the way he plans on doing it is more than adequate.
I would appreciate some advice, thanks in advance.
J
I have a local friend doing the building work and another company is supplying and fitting the conservatory.
Today I asked the conservatory company whether it's a problem putting the screed down after the roof had been fitted as I'm integrating UFH into the screed. He asked about base construction and I told him that the base was going to be mot hardcore, sand, 750mm Kingspan, Ufh, screed. He said it needs a 100mm concrete slab aswell.
I've spoken to my builder, and he seems pretty adamant the way he plans on doing it is more than adequate.
I would appreciate some advice, thanks in advance.