Hi all.
I am in the process of building a single storey rear extension to my house.
I was going to get the trench for the footings dug by hand myself but think at 53 i am a bit to old....any idea what the cost will be to dig out a 42 foot long trench?....i have a small gap that may be accessible with a mini digger.

Thanks.
 
Sponsored Links
mini-diggers cost about £40-60 for the day, will cost you more for the driver, plus the diesel. But should do it quite quickly.
 
You can get a weekend hire also. If you're going to use a digger, plan your approach and progress so that you're not having to bridge a trench.

Give some thought to your spoil.
Top soil - can you use it on-site? If not, can you use a seperate skip?
Sub-soil - are you going to hire a skip to remove it.
How will you transport the spoil around the site? Give some thought to hiring a dumper also. A dumper that can tip into a skip perhaps?

Also, can you clear for the floor slab at the same time?

About 2.5 years ago it cost me about £350 for digger & dumper weekend hire, (self drive). About £300 for 2 skips. Top soil was reused on site.

Perhaps the more experienced posters might confirm, but I think, budget-wise, a third of the cost of a new build goes in the ground.
 
This sized trench could easily be dug in a day provided there is room for a small dumper (about 5-6 feet).

You must make sure that the water stop cock in the road is serviceable. You must also mark out where any pipe runs or electric/gas/other services are.

You will need a large area to dump the spoil, either via skips or a plywood deck onto which the spoil can be heaped in preparation for a grab. I think most grab loaders load from the passenger side.

If you were to drive the dumper, a mate on the digger, the spoil removed by a grab loader, the whole thing dug out in a day, without any catastrophes and a lot of forward thinking, then you may get it done for less than a grand.

Don't forget to dig off the oversite as you trench back.
 
Sponsored Links

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top