Hi we have had the following specifications for our extension (kitchen and dining), picture attached.
We are put off by the drying time for the 63mm screed, which our builder said would take 100 days. We are having engineered wood flooring and no UFH. Could anyone advise please:
What's the quickest drying screed?
Or would you go with T&G chipboard? What would be the issue with T&G chipboard Vs screed?
Thanks in advance