Hi guys.
Did my first ever floor screed today on a small area about 1mx1m and 40-50mm deep.
I read that it has to be fairly dry, if you squeeze a handfull little to no water should come out. I squeezed the mix and no water came out however after trying to trowel it smooth the surface is soaking wet.
I laid it over freshly laid concrete that i i put down this morning.
Should i have let the concrete dry first?
Have i completley ballsed it up?
Should i rip the screed out now whilst its still not set or should it be ok?
Thanks
Did my first ever floor screed today on a small area about 1mx1m and 40-50mm deep.
I read that it has to be fairly dry, if you squeeze a handfull little to no water should come out. I squeezed the mix and no water came out however after trying to trowel it smooth the surface is soaking wet.
I laid it over freshly laid concrete that i i put down this morning.
Should i have let the concrete dry first?
Have i completley ballsed it up?
Should i rip the screed out now whilst its still not set or should it be ok?
Thanks