Ground floor DPM nightmare... what to do?!

hi @dazlight where you say "use a good vapour underlay" do you mean just do this without digging up the floor and doing the 2x10kg again (they basically didn't put enough down)?
And do you mean MVS/fball F78 / F77 over what's there atm OR dig up and start again? (knowing we can't go much higher with what's there atm...
 
@dazlight @crazydaze

have discussed with the company and we think a solution might be to bash out any bossed bit and fill.
Do another 20kg Ardex DPM1 over whole space and another layer of Ardex NA.
Around the external door we frame in a low lying doormat, and at the other 5 opening we will have to have some sort of profile to that there's not a 20mm step.....
Anyone see any issues with this?
Or are we definitely better to take it all up and start again??
 

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top