New screed floor being laid in new extension and existing part of the house. The walls are going to be float and set (not D&D plaster boarded).
The internet suggests the 25mm PIR upstand needs to be installed up to the DPC level. Which is roughly where our screed will go up to as well.
By the time the foam expansion strip (which is required for the screed) is added, this is quite a lot of build up off the wall - around 35mm. And would not be covered by the screed either?
Surely this would be visible on the perimeter of the finished screed floor?
Is this correct or am I misunderstanding how this is to be installed?
The internet suggests the 25mm PIR upstand needs to be installed up to the DPC level. Which is roughly where our screed will go up to as well.
By the time the foam expansion strip (which is required for the screed) is added, this is quite a lot of build up off the wall - around 35mm. And would not be covered by the screed either?
Surely this would be visible on the perimeter of the finished screed floor?
Is this correct or am I misunderstanding how this is to be installed?