We are having our 1990 built bungalow extended and renovated. The new 150mm concrete subfloor was laid in October.
The existing floor was stripped back to the concrete subfloor.
The subfloor was lined with VCL with 75mm Celotex on the new subfloor and 40mm on the existing.
Underfloor heating was installed through-out with 50mm of anhydrite self levelling screed poured on the 14th of December.
The bungalow didn't have any windows fitted until 10th of January so it was pretty well ventilated during that time.
The heat pump was installed on January 17th. Since January 18th it has been running a drying program where the water temperature in the underfloor heating system is ramped up progressively for 7 days to 45C and back down again for the next 7 days.
After the end of the drying program I intend to run the heating to achieve a constant indoor temperature of 18C.
On 7th of February, I have arranged to start the installation of the kitchen and bathrooms.
On 22nd of February, I have arranged to have click LVT flooring installed in all but the two bedrooms. The bedrooms will be carpeted.
Does this plan seem OK to you? Are there any precautions I should be taking?
From the 3rd day into the drying program there has been no condensation anywhere in the building.
I intend to start duct taping squares of polythene to the floor over-night and start checking for damp patches.
I am slightly concerned that the floor fitter does not possess a moisture meter. I have been trying to find somewhere I can hire a hood hygromoter, so far without success. Any recommendations? I would appreciate your advice.
The existing floor was stripped back to the concrete subfloor.
The subfloor was lined with VCL with 75mm Celotex on the new subfloor and 40mm on the existing.
Underfloor heating was installed through-out with 50mm of anhydrite self levelling screed poured on the 14th of December.
The bungalow didn't have any windows fitted until 10th of January so it was pretty well ventilated during that time.
The heat pump was installed on January 17th. Since January 18th it has been running a drying program where the water temperature in the underfloor heating system is ramped up progressively for 7 days to 45C and back down again for the next 7 days.
After the end of the drying program I intend to run the heating to achieve a constant indoor temperature of 18C.
On 7th of February, I have arranged to start the installation of the kitchen and bathrooms.
On 22nd of February, I have arranged to have click LVT flooring installed in all but the two bedrooms. The bedrooms will be carpeted.
Does this plan seem OK to you? Are there any precautions I should be taking?
From the 3rd day into the drying program there has been no condensation anywhere in the building.
I intend to start duct taping squares of polythene to the floor over-night and start checking for damp patches.
I am slightly concerned that the floor fitter does not possess a moisture meter. I have been trying to find somewhere I can hire a hood hygromoter, so far without success. Any recommendations? I would appreciate your advice.