Hello All,
Out of curiosity, lets say you are running a twin and earth cable from the CU in conduit (up 2m into a ceiling), clipping it to a joist in an insulated loft, then inside capping down to a 'point', which method would you consider it ?

Thanks for any advice.
 
Sponsored Links
If it were running in contact with insulation for more than 500mm, then Method 4.

If not in contact with insulation, Method 3.

If embedded direct into plaster or masonry, Method 1.
 
Thanks secure,

I suppose what I meant to say is do you put all the methods used in the circuits 'wiring' (in that tiny space on test forms :LOL: ) ??

Thanks for your time.
 
Sponsored Links
No, just the most severe, I expect, because when you design a circuit, you use the most severe method in the calculation.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top