Does anybody know the up to date length for which a PP is active when:-

1. PP is obtained following a routine application.

2. PP is obtained on appeal.
 
Sponsored Links
5 years. Unless, otherwise specified as a condition as part of the granted permission.
 
There is no difference for appeals and it's typically 3 years for both, but under the current economic climate 5 years is/may be being specified to allow jobs put on hold to start later
 
There is no difference for appeals and it's typically 3 years for both, but under the current economic climate 5 years is/may be being specified to allow jobs put on hold to start later

It was changed to three years from five years for regular applications some time ago but I was not sure about the appeal because someone suggested it was only two years!

Woody, where is it being considered about extending the time period?

How does one apply to extend an application approved on appeal?

Tony
 
Sponsored Links
If not already done so, the Government will consider the extension to five years and send out a circular to the local councils.

A decision on appeal is exactly the same as a decision from the council and the same time limits will apply

The only way to extend the permission would be to re-apply or make a "significant" start - eg lay foundations, and then there is no time limit to complete
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top