Hi,
I'm doing a full flat renovation (2 bed, 60 sqm). Apart from keeping external walls and some of the internal walls, everything is to be demolished and replaced with new ones.
Before it started, my contractor estimated the project to take 4 months. Now we are 3 months into the project and roughly 10 - 15 days behind schedule. The main reason is that the new Vaillant boiler arrived 3 weeks late. I don't really know the why it's late. My contractor manages supply.
At the moment, the workers are plastering walls and ceilings. The remaining things based on the project time table my contractor gave me 3 months ago:
Anyway, I'm not massively impressed about the progress. Could anyone give me some advice?
Thank you so much!
Patrick
I'm doing a full flat renovation (2 bed, 60 sqm). Apart from keeping external walls and some of the internal walls, everything is to be demolished and replaced with new ones.
Before it started, my contractor estimated the project to take 4 months. Now we are 3 months into the project and roughly 10 - 15 days behind schedule. The main reason is that the new Vaillant boiler arrived 3 weeks late. I don't really know the why it's late. My contractor manages supply.
At the moment, the workers are plastering walls and ceilings. The remaining things based on the project time table my contractor gave me 3 months ago:
- Plaster walls and ceilings - original plan is 2 weeks, but in reality only 25% was finished after 2 weeks - don't know why - 2 more weeks???
- Fit covings - 1 week
- Prepare walls & ceiling painting mistcoat - 1 week
- Install wooden floor (engineered wood, glued down) - 1 week
- Install internal doors, skirting boards and architraves - 1 week
- Painting and decorating walls and ceilings - 2 weeks
- Install kitchen cabinets (rigid), splashback and appliances - 2 weeks
- Install fitted wardrobes - 1 week
- Painting and decorating woodwork - 1 week
- Bathroom tiling, sanitaryware 2nd fix - 2 weeks
- Install radiators, TRV, thermostat - 1 day
- Electricity 2nd fix - 1-2 weeks
- Install a mist system for fire suppression (2nd fix) - external contractor - 2 days
- Install an air con - external contractor - 2 days
- Minor things - elec and gas test and certification, site clean-up etc - 2-3 days
Anyway, I'm not massively impressed about the progress. Could anyone give me some advice?
- I guess I should I push my contractor a bit. But how? I'd want them to be faster, but I don't want to sacrifice quality.
- What is a realistic timing of plastering the walls and ceilings for a 60 sqm 2-bed flat?
- How do you deal with project delays in general.
Thank you so much!
Patrick

