    I have some questions for the following work:

    1. New fuse board
    2. New electrical sockets (4 x double-sockets per room in 4 rooms)
    3. New wiring for lights
    4. New light switches
    5. Two lengths of Cat-6 in living room + 3 bedrooms
    6. Extractor fan in bathroom
    7. Power and lighting in loft
    8. Power and lighting in attached garage
    9. Security lighting front and back of property
    10. Smoke and CO sensors
    11. External power sockets

    What would typical costs be for the above (just a ballpark figure to nearest thousand pounds), how long would it take and would the electrician lift up floorboards and loft materials as required to do the job or would I have to have all the floorboards in the house lifted up prior to the job commencing?
     
  2. Sponsored Links
  3. RF Lighting

    RF Lighting

    Joined:
    31 Mar 2006
    Messages:
    19,108
    Thanks Received:
    1,225
    Location:
    Leeds
    Country:
    United Kingdom
    About the same as a second hand car.

    It would take between one and 5 weeks.

    The electrician will lift all the floorboards he requires if you pay him to. If you lift them then he will not have to.
     
  4. ajrobb

    ajrobb

    Joined:
    23 Jan 2010
    Messages:
    1,656
    Thanks Received:
    163
    Location:
    Sussex
    Country:
    United Kingdom
    OSG Appendix 8, Table 8B "Minimum number of twin socket-outlets to be provided in homes"
    size: small (up to 12 m²), medium (up to 25 m²), large
    main living room: 4, 6, 8
    dining room: 3, 4, 5
    single bedroom: 2, 3, 4
    double bedroom: 3, 4, 5
    bedsit: 4, 5, 6
    study: 4, 5, 6
    utility: 3, 4, 5
    kitchen: 6, 8, 10
    garage: 2, 3, 4
    conservatory: 3, 4, 5
    hallway: 1, 2, 3
    loft: 1, 2, 3
     
  5. Taylortwocities

    Taylortwocities

    Joined:
    28 Jul 2006
    Messages:
    18,665
    Thanks Received:
    1,861
    Location:
    Oxfordshire
    Country:
    United Kingdom

    :LOL:
     
  6. taz777

    taz777

    Joined:
    30 Jan 2011
    Messages:
    197
    Thanks Received:
    6
    Location:
    Middlesex
    Country:
    United Kingdom
    So, one electrical contractor reckons it takes two weeks to rewire a 3-bed semi. Another can do it in 3-4 days.
     
  7. 1john

    1john

    Joined:
    3 Oct 2009
    Messages:
    3,351
    Thanks Received:
    342
    Location:
    West Glamorgan
    Country:
    United Kingdom
    Suppose it either depends on the man power thrown at it or another way of looking at it is how rough you can slap it in. Ask the 3/4 day guy if he is willing to work with a penalty clause?
     
  8. Taylortwocities

    Taylortwocities

    Joined:
    28 Jul 2006
    Messages:
    18,665
    Thanks Received:
    1,861
    Location:
    Oxfordshire
    Country:
    United Kingdom
  9. DIYnot Local

    DIYnot Local

    Joined:
    3 Sep 2019
    Country:
    United Kingdom

    If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

    Select the supplier or trade you require, enter your location to begin your search.


    Are you a trade or supplier? You can create your listing free at DIYnot Local

     
  10. Sponsored Links
Loading...

Share This Page