• Looking for a smarter way to manage your heating this winter? We’ve been testing the new Aqara Radiator Thermostat W600 to see how quiet, accurate and easy it is to use around the home. Click here read our review.

sorry......... part p question

Joined
20 Dec 2004
Messages
1
Reaction score
0
Country
United Kingdom
Hello all,I am about to start a rewire next week but because of the christmas break it will not be completed until the first week in january.Will this be exempt from part p as i have heard as long as the job was started before jan 2005 and completed before april 2005 part p will not apply.
Thanks for any views.
 
Yes it's exempt.

All work started before 1st Jan and completed before 31st March is not notifiable.
 
And here's an example of more unenforcable nonsense.

How exactly, is Mr. Council Inspector going to know whether you started in 2004 or not? :roll:
 

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top