Steel beam and plasterboard

Discussion in 'Building' started by snapfish, 15 May 2019.

  1. snapfish

    snapfish

    Joined:
    15 Nov 2009
    Messages:
    32
    Thanks Received:
    0
    Location:
    Lincolnshire
    Country:
    United Kingdom
    I’ve just installed 4 steel beams in my house, do I still need to box them in with plasterboard if they are at joist level (the ceiling will be flush).
    The structural calculations only say 30 mins fire proof. If I were to use the fire retardant board on the bottom of steel, would that be enough?
     
  2. ^woody^

    ^woody^

    Joined:
    3 Sep 2006
    Messages:
    26,843
    Thanks Received:
    3,333
    Location:
    West Mids
    Country:
    United Kingdom
    The ceiling is 30 minutes
     
  3. snapfish

    snapfish

    Joined:
    15 Nov 2009
    Messages:
    32
    Thanks Received:
    0
    Location:
    Lincolnshire
    Country:
    United Kingdom
    I think I follow. So if the whole ceiling is rated at 30mins, there is no need to put plasterboard on the sides of the beam?
     
  4. ^woody^

    ^woody^

    Joined:
    3 Sep 2006
    Messages:
    26,843
    Thanks Received:
    3,333
    Location:
    West Mids
    Country:
    United Kingdom
    The idea is to protect the beam from a fire in the room below it, so if there is a ceiling between the room and the beam, that is normally sufficient.
     
  5. domdee

    domdee

    Joined:
    29 Nov 2016
    Messages:
    77
    Thanks Received:
    12
    Country:
    United Kingdom
    intumescent paint might be an option
     
  6. Leofric

    Leofric

    Joined:
    9 Nov 2018
    Messages:
    1,668
    Thanks Received:
    139
    Country:
    United Kingdom
    Didn't the person who did the structural calculations advise you that structural alterations such as installing 4 steel beams require building regulations approval ? Building Control would then see what fire protection was being proposed to achieve 30 minutes fire resistance !
     
  7. snapfish

    snapfish

    Joined:
    15 Nov 2009
    Messages:
    32
    Thanks Received:
    0
    Location:
    Lincolnshire
    Country:
    United Kingdom
    Yes, we had building control out end of last week, to check the beams. Only thing he picked up on, was the joist hangers didn’t have a screw in every single hole. Which is easily fixed. We ask about the plasterboard, and he said standard 12.5mm is rated at 30 mins so is happy for us to single lay board and skim the whole ceiling.
     
  8. Notch7

    Notch7

    Joined:
    15 Sep 2017
    Messages:
    13,658
    Thanks Received:
    1,066
    Location:
    Sussex
    Country:
    United Kingdom
    I always thought it was 2 layers of standard or one of 'pink board'.......
     
  9. 23vc

    23vc

    Joined:
    17 Apr 2015
    Messages:
    1,457
    Thanks Received:
    193
    Location:
    Warwickshire
    Country:
    United Kingdom
    Me too
     
  10. John D v2.0

    John D v2.0

    Joined:
    26 Aug 2016
    Messages:
    5,834
    Thanks Received:
    789
    Country:
    United Kingdom
    Our se specified double board but the builder did pink board which was fine and saved some space.
     
  11. DIYnot Local

    DIYnot Local

    Joined:
    3 Sep 2019
    Country:
    United Kingdom

    If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

    Select the supplier or trade you require, enter your location to begin your search.


    Are you a trade or supplier? You can create your listing free at DIYnot Local

     
Loading...

Share This Page