Hi
Two days ago I had my block and beam balcony screeded. I told the screeder that it needed a fall from 80mm to 40mm going away from the house.
Today the bricklayer discovered that the screed was virtually level with a run off of about 10mm! going from 60mm to 50mm down to a proposed drainage hole
Apart from breaking it up and starting again, and arguing with the screeder, are there any alternatives?
The builder mentioned floor leveller but the area affected is about 12m2
Can it be re screeded laying an additional 10-20mm over the new screed bonding it with PVA etc
Cheers
Two days ago I had my block and beam balcony screeded. I told the screeder that it needed a fall from 80mm to 40mm going away from the house.
Today the bricklayer discovered that the screed was virtually level with a run off of about 10mm! going from 60mm to 50mm down to a proposed drainage hole
Apart from breaking it up and starting again, and arguing with the screeder, are there any alternatives?
The builder mentioned floor leveller but the area affected is about 12m2
Can it be re screeded laying an additional 10-20mm over the new screed bonding it with PVA etc
Cheers