What is the correct method for installing padstones and steel pfc

Discussion in 'Floors, Stairs and Lofts' started by Lisa Stephens, 10 Sep 2016.

  1. Lisa Stephens

    Lisa Stephens

    Joined:
    10 Sep 2016
    Messages:
    3
    Thanks Received:
    0
    Country:
    United Kingdom
    I have just started my own DIY loft conversion. I have already obtained planning permission and building regs permission.

    I removed all of the rubbish from the loft and then had scaffolding installed.

    The structural engineer drawing specifies three loft pieces of PFC steel beams which are 4.9M in length. Each steel beams sits on one C35 concrete padstone 450 X 225. I searched (Googled) for these online but I kept finding 440 X 215 sized padstones. Are these padstones the same thing?

    I am also unsure on the method of installation of the padstones. Do I first install two rows of Class B engineering bricks, followed by the padstones and then the steel? The steel company quoted £600 for all three steel beams. I'm not sure if this is a bargain or not?

    I did ask them to install the steel beams, but they told me it wasn't economical because it's only three pieces of steel.
     
  2. Sponsored Links
  3. tony1851

    tony1851

    Joined:
    23 Feb 2012
    Messages:
    9,883
    Thanks Received:
    1,483
    Location:
    Manchester
    Country:
    United Kingdom
    The 440 x 215 padstones would be OK for a domestic loft conversion.
    The SE would have sized them to go direct onto your existing brickwork - no need to put engineering bricks in first.
     
  4. Lisa Stephens

    Lisa Stephens

    Joined:
    10 Sep 2016
    Messages:
    3
    Thanks Received:
    0
    Country:
    United Kingdom
    Thanks for the answer Tony1851. I have got a few more questions to ask.

    Is a 3:1 ratio of sand cement accurate for a padstone mortar bed?

    After I lay the padstones, how long should I wait before laying the steels on top. Is there a recommended amount of time to wait in order for the mortar to fully dry?

    Are the steels layed on the padstones with or without mortar being applied?
     
  5. John D v2.0

    John D v2.0

    Joined:
    26 Aug 2016
    Messages:
    6,315
    Thanks Received:
    876
    Country:
    United Kingdom
    Steels go directly on the pad stones, you have to let the mortar go off before putting any load on, but don't trust us on here, your SE should specify as he has professional responsibility for correctness.
     
  6. tony1851

    tony1851

    Joined:
    23 Feb 2012
    Messages:
    9,883
    Thanks Received:
    1,483
    Location:
    Manchester
    Country:
    United Kingdom
    As above - nothing between steel and padstone. 24 hours should be fine.
     
  7. JobAndKnock

    JobAndKnock

    Joined:
    30 Sep 2011
    Messages:
    4,795
    Thanks Received:
    1,027
    Location:
    Lancashire
    Country:
    United Kingdom
    On the rare occasions when we need to add packers we tend to use solid steel shims which come from structural steel fabricators in various thicknesses.
     
  8. DIYnot Local

    DIYnot Local

    Joined:
    3 Sep 2019
    Country:
    United Kingdom

    If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

    Select the supplier or trade you require, enter your location to begin your search.


    Are you a trade or supplier? You can create your listing free at DIYnot Local

     
  9. Sponsored Links
Loading...

Share This Page