Dear all,
We are currently planning to have the following work done: 1. new boiler and radiators (remove water tank), 2. ceiling/wall skimming, 3. chimney lining and wood stove fitting, 5. spot lights as well as 6. painting of walls.
Now my question (which might be obvious to a lot of you but not to me): What order should this be done in? I know that painting of walls comes last but that's about it
Thank you