I had my footings dug out and just had the concrete poured last week.
I've been checking the measurements as I was going to start building and it's quite a bit out. 35cm!
It's needs to go 35cm to the right (blue arrow). The block is right on edge of footings.
It was dug out by digger with driver.
The neighbour conservatory footings are on my side of boundary (red line)
I don't want to come in because I have already come in by 70cm on left side for access around back.
What's best way dealing with this?
I had my footings dug out and just had the concrete poured last week.
I've been checking the measurements as I was going to start building and it's quite a bit out. 35cm!
It's needs to go 35cm to the right (blue arrow). The block is right on edge of footings.
It was dug out by digger with driver.
The neighbour conservatory footings are on my side of boundary (red line)
I don't want to come in because I have already come in by 70cm on left side for access around back.
What's best way dealing with this?