I'm building a kitchen side infill extension and so far have moved drainage, dug footings and filled with concrete. I am now digging the over site down to the concrete foundation level. What is the best form of construction for the first few courses of bricks/blocks? Should I use engineering bricks straight on to the concrete footing? Or should I use concrete blocks first? What is best?